HERA-B Time Schedules
The time schedules of the HERA-B experiment are making use of the
Microsoft program "MS Project 4.0".
This original plan is shown as the upper green bar which is called "baseline".
The lower (light blue) bar shows the required time according to the
actual planning and can be modified. This actual bar is filled with
dark blue in order to indicate the progress made. As a consequence,
the dark blue bar should always end at the dashed vertical line
indicating the present date.
Most of these files are pdf-files.
Installation Schedules
Installation '94 -'96 (final)
Installation '96 Summary (final)
Shutdown '96/'97 (final)
Installation '97 -'98 (final)
Installation '98 (final)
Installation Christmas break '98/99
(final)
Installation '99 (14/07/99)
Installation mini shut-down 7/99 (21/09/99)
Installation mini shut-down 8/99 (21/09/99)
Installation mini shut-down 9/99 (21/09/99)
Installation mini shut-down 10/99 (07/10/99)
Installation mini shut-down 11/99 (04/11/99)
Installation mini shut-down 12/99,(02/12/99)
Winter shut-down 99/00, (19/1/00)
Installation mini shut-down 03/00
Installation mini shut-down 05/00
Lumi shut-down (06/08/01) as pdf-file
See as well
Hera-B and the Lumi shut-down (talk)
. (The time schedule in this talk has not been updated.)
Maintenance day 13/08/01 (07/08/01)
Add. maintenance day 10+11/09/01 (11/09/01)
Maintenance day 24/09/01 (25/09/01)
Maintenance day 19-21/11/01 (22/11/01)
Xmas shut-down 21/12-22/01/02 (15/01/02)
Edited by J. Spengler, latest update 08/01/02