Draft - HERA-B Commissioning and Run Plans

Author: K. Ehret

last update: June 14. 2001 (M. Medinnis)

Plans for Sept 01 until May 02
 
Sept. 01 Oct. 01 Nov. 01 Dec. 01 Jan. 02 Feb. 02 Mar. 02  Apr. 02 May 02
Goals & 
End of the 
month
milestones
subsystems technical 
operational
1. established target operation & VDS pot movement
2. common stable "dry" operation of  complete detector
1. 1st test data with complete detector on tape
2. reasonable good workingpoints established
1. stable common DAQ
2. reliable DQM
1. good calibration & alignment
2. Online reconstruction in operation
1. Gold. Min Bias run
2. stable pTr + SLT operation:
3. 1000 J/Psis on   tape
1FLT-2SLT track trigger in stable operation 1FLT-2SLT track trigger effic. understood 1. PRC
2. production run
Activities technical operation of SC, gas, readout, ...
noise, dead channels,
cabling tested & fixed
- 1 week of commontechnical operation without beam
"dry run"
- fix problems
- revise docu
- SD specific calib runs - ECAL calib
- ITR HV training
- VDS/ITR spars. (SLT)
- common data  taking
- ECAL calib & ITR HV training
1. take a muon enriched data sample (1 week, SLT): complete  detector (incl. ITR) 1. Golden Min Bias run (1 week)

2. prepare for pTr + SLT operation: 
1 week stable running (DAQ) with pTr + SLT

1. dedicated FLT 
  commissioning
2. first 1+2 track
  production run
... 1. 1+2 track production run
 various wire comb.
2. prepare FLT usage of ITR and muon pixel and study FLT pair trigger
Data taking standalone tests common operation test runs
(MinBias)
Common MinBias Common MinBias + SLT pTr+SLT pTr+FLT+SLT ... pTr+FLT+SLT
Trigger
System
...
...
pTr: calibration 
FLT: spy mode 
SLT: checks
pTr: use data to study
muon eff.
FLT: spy mode
SLT: checks
pTr: use data to study muon eff.
prepare for operation:
  calib., lookup tables
FLT: spy mode
SLT: prepare for operation
pTr: stable operation
FLT: spy mode (2.TFU)
SLT: commissioning, alignment needed
pTr: stable op.
FLT: startup
SLT: stable op.
... - stable operation (production) of  baseline 1+2 track trigger
- FLT studies
Coordination
Tasks & Run 
Coordination
1. activities under subsystem responsibility
2. anticipate periods without beam, e.g. HV
3. DQM definition documented
1. organize "dry run" with SG
2. DQM machinery operational
3. revised usable shift docu (RC&SG)
4. detailed run & shift plan until end of 2001
1. collect and reviewcomm. needs of SG
-> detailed run plans
2. regular RC meetings
3. usable DQM 
1. routine running
2. prepare run & shift plans until April 02
consider &  prepare in detail trigger commissioning steps routine  routine routine routine
Shifts none experts for "dry run" reduced shifts [1] 4 WoB 80 HS & 
n ES & m EoC
2 WoB:
80 HS & ESs, EoCs
3 WoB:
120 HS & 
n ES & m EoC
4 WoB:
160 HS & 
n ES & m EoC
4 WoB:
160 HS & 
n ES & m EoC
??? 4 WoB:
160 HS & 
n ES & m EoC
HERA startup phase test operation, tuning Lumi test run
(5 weeks)
periods with stable beam & target operation
Lumi Run 
(2 weeks)
Polarization tuning stable Lumi stable Lumi 4 weeks break
e+ -> e-
Lumi e-- p
Analysis
Issues
--- --- analysis of MinBias data: calib & align.
-> feedback
- calibration
- alignment
- FLT studies
- muon eff
- pTr efficiencies
- Gold. Min Bias run
- J/Psi eff., resolution - J/Psi
- FLT
- FLT efficiencies Physics

 General Remarks

* FLT incl. pretriggers: useful dedicated shorter studies are possible in each stage
    and will be handled with some priorities

* default trigger for 2002: 1 track from FLT + 2 tracks inside SLT (muon and electron pTr tracks)

* after this: include ITR and muon pixel into FLT, study FLT pair trigger, commission high multiplicity Veto